Project: CAROLINE SPRINGS SQUARE STAGE 3, VIC

Caroline Springs Stage 3

Project Description

The Caroline Springs Square stage 3 Development is 6,500sm and saw the addition of a supermarket, large format discount store, car wash, more than ten specialty stores and expanded amenities including a new parents’ room.

Enhanced pedestrian access and additional car parking spaces all formed part of this project.

Hydraulic scope of works:

  • Connection to the existing Caroline Springs Square services
  • Installation of sewerage systems
  • Installation of water pumps
  • Sanitary plumbing including the provision of fixtures and fittings
  • Installation of Thermostatic Mixing
  • Valves for the delivery of tempered water
  • Storm water drainage
  • Hot and cold water reticulation and metering
  • Fire service ring main upgrade
  • Trade waste drainage

Overcoming Challenges

  • Excavation in rock – over 900 cubic Meters of rock removed
  • Working within a live shopping centre environment
  • Constructing a deep sewer bore under a 4-lane road crossing

Major Achievements

  • The development achieved a 4 Star Green Star Design & As Built rating based on the Centre’s sustainability performance across energy and water efficiencies, design, liveability, environmental quality and innovation

Sector

RETAIL

Client

LEND LEASE

PROJECT VALUE

$ 1.9 MILLION

Location

CAROLINE SPRINGS, VIC

COMMENCEMENT

FEBRUARY 2017

COMPLETION

DECEMBER 2018